High Voltage Cabling

CASE STUDIES - HIGH VOLTAGE CABLING
Client: Scottish Power
Location: Dalmarnock, Rutherglen
Job Description: Preparation for 2014 Commonwealth Games: diversion of existing 132kV overhead lines towers
Main Contractor: NKT Cables / Enterprise plc
OUR ROLE: testing of previously installed ducts by others; excavation, re-instatememnt of all associated HV joint bays; installation of:
- Dalmarnock 275kV SS to St Andrew's Cross SS:
- 6.5km x 2 132kV circuits and associated pilot cables
- 52km single core cabling
- 12.5km comms & pilot cables
- Dalmarnock SS to Cartyn Termination Tower:
- 21km x 132kV cabling
- 5.5km comms & pilot cabling
- Dalmarnock SS to Camberslang SS:
- 27km 33kV cabling
- 7km comms & pilot cabling
Duration: 100 man months
Date: 2012
Reference: available on request
Client: CE Electric (YEDL)
Location: Gainsborough
Job Description: 33kV Cable Diversion
Main Contractor: Bethell Power
OUR ROLE: radar surveys, excavation, installation & reinstatement of 2 x 33kV circuits for 1.9km o public highways & agricultural land
Duration: 24 man-months
Date: 2008
Reference: available on request